November 3, 2014

Citadel Rig 2 Construction Update

Citadel's Construction and Maintenance Manager, Barry Little, is working tirelessly on Rig 2's construction. Having a full complement of crew in place by the first week of November, it will be "all hands on deck" to ensure Rig 2 is on schedule.

 

Here is a sneak peek at Rig 2's progress:

  • The mast is together and the stringing of lines and blocks are complete  
  • The pumps are wired in and piping is being assembled for pumping purposes
  • The substructure has been painted and should be back at the rig-up yard by the last week of October
  • All generators have been run and load-tested
  • Commissioning of cyber-chair and drawworks is underway
  • Rigging in all controls for wrench and top drive is underway
  • Working towards a mid-November rig move

Citadel is excited for Rig 2 to join its active fleet. Stay tuned to the Knowledge Box for further Rig 2 updates.